Welcome to the Hillcrest Turf Blog. As our blog grows and develops we are creating a "year in review" and the blog with pictures and articles related to different problems and successes during the growing season remind us of the many improvements Hillcrest under goes every season.

Monday, June 27, 2011

#17 cart path demolition..............

Today we started tearing out the asphalt cart path near #17 green.

Tomorrow we will do some more dirt work and set forms for our first pour which will cover about 100 feet. All of our plans depend on weather but I plan to pour on Friday and re-open the path for carts on Sunday.

My original plan was to pour on a Monday morning but being that the next Monday is the 4th of July that would
extend the project futher into July than I care for.

The second pour, measuring some 220 feet will be poured at the same time. Hopefully on a Saturday morning. I will post more updates as we get more finished.


































No comments:

Post a Comment