Next week Monday we will be starting the annual irrigation blowout. The process takes about 3.5 days.
This week we mowed all the short grass one last time and then pulled all the reels off of the traction units. So I dont plan to mow anymore this season. The bathrooms should be winterized and shut down for the season by the weekend. Most of the rakes, t-signs, tee markers, ballwashers, etc. have been brought indoors too.
Following blowout we still need to make our snowmold application and topdress the greens. We also will be working on the leaf harvest, but that has been a waiting game as the trees are not dropping leaves real fast yet.
Keeping you better informed about daily tasks, project progress, and course conditions.
Welcome to the Hillcrest Turf Blog. As our blog grows and develops we are creating a "year in review" and the blog with pictures and articles related to different problems and successes during the growing season remind us of the many improvements Hillcrest under goes every season.
Thursday, November 3, 2011
Tuesday, October 25, 2011
New tees????
Here are some new locations for ladies tees in 2012. Hole #6 could be 50+ yards shorter (125 yards) and #16 could be as much as 60 yards shorter (120 yards) than the current tee boxes if this project is approved.
I have often believed that the ladies tees were positioned too far back and also believe that the tee space on our par 3's is too small. The construction of new tee's on these two par 3's allow for more tee space for the men and a more comfortable hole for the ladies.
My plan is to cut these areas down to tee height (did that today as you can see in the pictures) and when construction begins save the sod so the tee can be put into play as soon as possible. We want to excavate a larger area then you see in the picture so we can elevate the tee slightly and of course be left with a flat tee.
No time table is set for this project because it has not been approved yet. I would like to get #16 done early in the summer and #6 (requires more fill) completed late summer or early fall.
Friday, October 21, 2011
#8 drainage project complete.................
We are also working on building 1 and maybe 2 new tees next year on #6 and #16 for the women. While nothing is approved I will be working on exact placement, size, and distance heading into the winter months.
Friday, October 14, 2011
Wednesday, October 12, 2011

It would be better for the future if I took before and after photos from the same spot and with the same camera. It would make the differences a little easier to see.
#8 drainage project update.....
Monday, October 10, 2011
#8 drainage project......
If things dry up on the site we could get most of our grading finished tomorrow and start trenching on Wednesday.